Pumphouse
Project carried over to next spring: update by Doug Corkery,
29th October, 2006:
The
pumphouse construction has ceased until spring. City staff are
intransigent vis a vis a security fence and limiting access to
the site. Recent meetings between staff, Councillor
Holmes' staff and the NCC have not resolved this conflict. My
understanding is 1. NCC are insisting on a lower and more
decorative fence closer to the water 2. Diane Holmes supports
this option and the landscape architect firm has been instructed
to draw up plans for some type of a 4 ft. fence to follow the
perimeter of the pathway around the circumference of the
tailrace. This will result in the pathway being inside the
fence. It is our understanding that a committee of council will
have to overturn Recreation and Parks staff to approve this
fence proposal. Our access agreement is to some extent
contingent on the fence. As for the building, we have submitted
all of our plans to the NCC. Until the other plans have been
agreed upon, the NCC planners and land management staff are not
able to stamp our plans. We hope to make progress on all fronts
after the municipal election and over the course of the winter.
The “Last” Word on the LeBreton Tailrace
course, by D.C. 20 March, 2006
With minor editing, I could
be writing the same article this year as I have written the last
several years. Tailrace construction was scheduled to start in
earnest early last fall and be completed before Christmas. Cash
flow problems resulted in the City delaying work until late
January. At press time the embankments are pretty much finished
and contaminated soil removal is complete. The water is
scheduled to be on anytime now. That’s the good news such as it
is. The project has become more complicated than anyone would
have anticipated. Read on.
Landscaping is now scheduled to start in May and it is
anticipated to be complete before the summer. The City has
agreed to install permanent posts for gates and we hope to have
permanent gates up sometime this summer. Because of the delays
last fall, many of our obstacles were not properly stabilized
and we were not given permission to do the work ourselves. The
City has retained the services of an engineer to look at this
problem and has agreed to do the stabilization work next fall at
their expense along with installing access points into the water
with steps at appropriate put-in spots. The City has
recently discovered that the pumping station foundation has been
eroded by water from the aqueduct. Because of this, they
anticipate a prolonged shutdown this fall to stabilize the
building. During this window, they plan to complete all of the
Tailrace work as well.
I am pursuing the construction of a storage building with the
National Capital Commission. To this end, Sheryl Boyle is
drawing up landscaping plans in conjunction with the landscape
architects engaged by the City for the Tailrace area. The City
will submit the plans to the N.C.C. for approval. The plan will
include an emergency vehicle access on the east side of the
Tailrace which will go down the hill to the flats close to where
our containers are currently situated. The proposal is to locate
the building, a temporary prefab steel 30 x 50 ft. structure
between the service road and the cliff just south of the
containers. If approved, the building will have storage for a
large number of boats as well as change rooms and lockers. There
will be no services to the building. Cost will be around
$40,000. We are looking into grant possibilities to raise part
of the capital.
The City Recreation and Parks Department have not come to terms
with how to control access to the site, something they are very
concerned about. They have approached this in a risk averse way
and would prefer to limit public access. To this end, they wish
to install a 6 ft. security fence around the perimeter of the
site and restrict access including no events of any kind. A
second concern that they have is the proposed rapid transit
train construction scheduled to begin sometime in the next two
or three years. Plans at present call for a central switching
hub at the Bronson, Slater, Albert, Commissioner intersection.
Juxtapose this with the N.C.C.’s recent announcement of a
fireman’s memorial for the northwest corner next to the
Tailrace, the City Fire Dept.’s plan to share our site as a
swiftwater rescue training facility and the N.C.C.’s insistence
on reinstating the Trans-Canada Trail under the Pooley Bridge
and along the eastern Tailrace embankment and you begin to
understand where this is going. Councillor Holmes, the local
community association and the N.C.C. do not support the City
Recreation and Park plan for a security fence. Our proposal for
a low safety barrier close to the water is more consistent with
their vision for the area. Based on all of the above, the City
Recreation and Parks Dept. have not been forthcoming with an
access agreement. Given that the City only owns a small strip of
shoreline on either side of a public waterway surrounded by
N.C.C. property, it is my opinion that they will have to
compromise.
So what does it all mean for this year? My best guess based on
all of the above uncertainty is that we will be able to install
some temporary gates and put up with some deficiencies in the
quality of the eddies etc… this year. We may only be able to
access the site before and after construction hours until the
summer. This fall, there will be a prolonged dewatering
permitting completion and tuning up of the site as well as
building construction. No events will be possible until next
year. This is my best guess. Given all of the above, much could
change between now and then.
“WHAT’S HAPPENING AT THE PUMPHOUSE?
By D.
C., 30 March, 2005
Can we /
why can’t we paddle there? I just want to set up a few wires.”
As most of
you are no doubt aware, Jamie Cartwright, Michal Staniszewski
and myself representing the Club, met with Mayor Chiarelli and
his entourage in early January. Joseph Potvin, representing
Whitewater Canada was also in attendance. As a result, the City
endorsed the site as a training facility.
Much work
remains to be done. Construction will continue this spring,
after the snow melts, with completion of the embankment
stabilization on the northeast side at the bottom of the bowl. A
new sidewalk will be installed under the Pooley Bridge arch, and
tree planting and other landscaping measures will take place.
Because of
this, the site remains the responsibility of the site
contractor, and it is unrealistic to imagine that any contractor
would take on the liability risk of having recreational paddlers
of all ages on a construction site.
This
construction will be completed sometime this summer. However,
the water will be shut off from early July to late fall at the
earliest, for replacement of clean water pipes from the Lemieux
filtration plant to the Fleet Street Pumping Station and Station
upgrades. This is a $52 million dollar project. As such, we have
been promised access in spring of 2006.
The City
and consulting engineers, Robinsons & Associates have been
extremely accommodating. They have made every effort to
duplicate the existing shoreline and eddies in every way
possible. The new embankments are finished with rounded
fieldstone on a 45 degree slope. Over $2 million has been spent
to date on contaminated soil removal and embankment
stabilization.
In
consultation with the Department of Fisheries and Oceans, we are
fairly confident that the contractor will slot in armour stone
steps into the water every 10 meters or so, on both sides of the
tailrace for easy access. The City has also agreed to installing
3 inch-diameter/10 foot-high steel posts every 10 meters along
the length of the site at the edge of shoreline pathways, thus
allowing us to cable the whole site and permit easy installation
of cross-wires and gates. The 2 meter wide pathways running
almost the full length on both sides should be a boon for
coaches and spectators.
We are
requesting that riprap be placed around the bases of all the
obstacles to prevent erosion. Also, several obstacles require
replacement or tune-up as they have settled or been removed
during recent construction. Again, the City engineers appear
receptive to our requests. So that’s the good news.
The City
of Ottawa Recreation and Parks Department are responsible for
our continued use of the site as a training facility. This is a
completely new sport for them. They are understandably concerned
about liability and risk to the general public at this site. As
such, they are in the process of developing a plan and a legal
framework to permit our continued use of the site in 2006.
At
present, their tentative plan is to fence the whole area so that
the public cannot be too close to the water’s edge, and we will
presumably have a key to a gate. As I have told them, I am of
two minds about this arrangement. From a Club perspective, who
could complain about having your own private secure paddling
facility in downtown Ottawa? My concern is that the general
public shouldn’t be denied access to a unique and historically
important piece of public property.
While we
would like to have slalom participate in the Ontario Summer
Games scheduled for Ottawa next summer, the Recreation & Parks
Department are presently reticent to permit any events on the
site. The department also has concerns about the impact the new
O-Train route (on Albert running east-west, just south of the
pumping station) will have on us.
We are
also attempting to negotiate permission to replace the shipping
containers with a prefabricated building (at our cost), with a
capacity for several hundred boats, and changing rooms. Parking
also remains contentious. The Recreation and Parks Department
are planning a meeting with the paddling community sometime in
mid-April on a weekday evening location and time TBA. Watch for
it in your e-mail.
In the
meantime, we have to get by with our flat-water gates,
occasional sojourns to whitewater slalom sites and getting back
to our roots, e.g., paddling more rivers. With a little luck
2005 should be a good year, and 2006 will be over the top.
Photos taken 12
April 05